Orion were asked to inspect the floor of a new sub station building by SSE and advise on a repair method.
Upon inspection it became apparent that the floor had not dried sufficiently before the floor paint system had been installed.
The client asked Orion to repair the floor. All loose paint was scraped back and dryers were set up in the building for several days prior to the works to dry the floor out thoroughly.
The paint colour was matched and the floor was patch repaired using a two part paint system with anti slip medium applied in the top coat.